compass Architect: Calfordseaden
location Location: Houghton Regis
crane Main contractor: TSL
subcontractor Sub contractor: FK Group
calendar Completion Date: 12 Jul 2023
The construction of Lidl's largest Regional Distribution Centre (RDC) in both Great Britain and globally has brought 125,000m2 of class B8 storage to the new 58 acre facility - located just outside London on the M1.

A new distribution hub servicing more than 150 Lidl stores in London and the surrounding counties, this RDC is the first to feature automation, bringing over 1,200 jobs to the Luton and Dunstable area.

Challenge

Full envelope construction provider FK Construction were contracted to construct the building envelope, cladding the building with Kingspan KS1000MR composite wall panels, fixed back to ultra heavy steel.

Solution

Being a secret fix panel, the fasteners needed to fasten through 100mm of insulated panel to fix back securely to the framing. We supplied in the region of 500,000 of our DF25-SSA4-HT fasteners for the construction of the external walls and internal coldstore applications, being able to self-drill through steel up to 25mm thick.

Hex headed, available with washers for roof, rooflight or wall applications, and in A4/316 grade stainless steel for maximum corrosion resistance: these fasteners are the solution for fixing into ultra heavy steel.

(images courtesy of FK Group)
“FK have forged a close working relationship with Fixfast over many years and in partnership successfully delivered a number of high-profile schemes. ”
Alistair Bolton Construction Procurement Director, FK Group